There was major visual progress this week! We started with most of a building and ended with nothing but the foundation.We took down the walls by cutting them into sections and then pulling them down with rope. It was like a giant tug of war chain, only there is not other team. Below is a video of some of the walls coming down. Big thanks to Sahar our video editor as well as Sam and Ariel who produced multiple angle shots.
|
After the walls fall we have to process the walls. We descend on the wall like locusts. We remove the lathe, pop-off the clapboard, and move the studs to the pile. |
Here are a few series pictures of the progress this week.
|
Beginning of the week, the roof and trusses are totally gone. |
|
Mid-way through Wednesday |
|
End of Thursday, all that remains is the floor. |
|
End of day Friday, the sub-floor, joists, and beams are totally gone. Left with the foundation and the basement walls. |
|
|
|
Another series from the south side.
|
At beginning of week, the unstable portion has been removed but most of the walls are still up. |
|
Mid Wednesday, the long walls have been taken down in sections, all that remains is the corners. |
|
Thursday, walls are down, the floor is still intact. |
|
Sub-floor carefully removed, we took care not to damage the tongue and groove by taking it out all together working simultaneously on a single piece to pop it up all at once. |
|
View of the floor joists and beams totally removed by the end of Friday. |